king marriot waste water project

King Marriot Waste Water Project

Client : CAPWO
Location : Alexandria Governorate            
Date : 
           - King Marriot (A&B) - 4/2009
           - King Marriot (C) – 9/2007
Duration : 
           - King Marriot (A&B)  - 36 months
           - King Marriot (C) – 15 months
Cost : 
           - King Marriot (A&B) – 400 million
           - King Marriot (C) – 38 million
Scope : 
         - Review shop drawing and documents, site
             supervision for all civil, electro-mechanic, and
             infrastructure works