Upgrading and rehabilitation for Tanta new water purification plant with capacity from 120,000m3/day to 175,000m3/day and water network for total area 16 feddan

Upgrading and rehabilitation for Tanta new water purification plant with capacity

Client : CAPWO

Location : Tanta city – Al Gharbia governorate

Date : 2008

Duration : 30 months 

Cost : 350,000,000 EGP

Scope :
 
-Design drawings, review documents, site supervision and program management for electro Mechanical and infrastructure work