Abu Oweikal transmission line with a total length of 36 km and purification plant with a capacity of 500,000 m3/day

Country :

‎ Egypt

Client :

Construction Authority for Potable Water and Waste Water

Project Value : ‎

1.4 Billion EGP

Owner :

Greater Cairo Water Company

Start/End Date :

2008-2020

Project Description :

Project consists of Intake pump station, booster pump station, Purification plant and two Transmission lines

-        Intake pump stations include 4 pumps with capacity 2000l/sec and 120 m head

-        Booster pump station includes 4 pumps with capacity 2000l/sec and 21 m head

-        Water purification plant capacity 500,000 m3/day

-        Two Transmission lines with 16 Km length each.

Each line is of 1400mm diameter and 16 bars operating pressure.

Services provided :

-        Design calculations and detailed drawings

-       Preparation of tender documents.

-       Review, Approval of shop drawings, technical submittals & As-built drawings.

-      Construction supervision.

-    ESIA

- Operation & maintenance supervision of water purification plant