El Mahla El Kobra wastewater plant 280,000 m3/day

Country :

Egypt

Client :

National Authority for Potable Water and Sewage

Project Value : ‎

1.68 Billion EGP

Owner :

Gharbia Potable Water & Sanitation Company

Start/End Date :

2008-2010

Project Description :

The project consists of design review, preparation of shop drawings and contraction supervision of wastewater treatment plant with capacity 280,000 m³/day Tertiary treatment for reuse including sludge handling units.

Services provided :

- . Design calculations and detailed drawings
- Preparation of tender documents.
- Review, Approval of shop drawings, technical submittals & As-built drawings.
- Construction supervision.