Abu Rawash (Rehabilitation & upgrade) with a capacity of
1.6 million m3/day extendable to 2 million m3/day
Country :
Egypt
Client :
Orascom Construction & Aqualia JV
for Construction Authority for Potable Water and Wastewater (CAPW)
Project Value :
3.5 Billion EGP
Owner :
Giza Potable Water & Wastewater Company
Start/End Date :
2018-2022
Project Description :
- Upgrading and rehabilitation of the existing wastewater treatment plant with capacity 1,200,000m3/day
- Extension works for the WWTP with capacity 400,000m3/day to reach total capacity 1,600,000m3/day (Secondary treatment)
Services provided :
- Design calculation and detailed design
- Preparation of work shop drawings & As-built drawings.
- Technical support during construction.