Badr City Sewage Force Main line from Badr City to New Admin City treatment plant

Country :

Egypt

Client :

Badr City Authority - New Urban Communities Authority (NUCA)

Project Value : ‎

900 million EGP

Owner :

Badr City Authority - New Urban Communities Authority (NUCA)

Start/End Date :

2020- present

Project Description :

Badr city sewage project consists of: - - Main pump station no (8) with capacity 1000 l/s first stage – 2000 l/s second stage & Force mains with diameter 1200 mm ,10.50 Km length, including valve champers and crossings
- Main pump station no. (7) with capacity 900 l/s first stage – 1800 l/s second stage & Force mains with diameter 1000 mm ,13.0 Km length, including valve champers and crossings
- Secondary pump station with capacity 280 l/s first stage – 570 l/s second stage & Force mains with diameter 700mm, 3.5 Km length, including valve champers and crossings
- Gravity sewer pipe lines with diameter (200-2000 mm) and 8 km length.

Services provided :

- Design calculations and detailed drawings
- Preparation of tender documents.