Marsa Alam City
Desalination plant 3000 m3/day – 10,000 m3/day
Country :
Egypt
Client :
Red Sea Housing Authority- Central Agency for Reconstruction-
Ministry of Housing, Utilities & Urban Development
Project Value :
35 Million EGP
Owner :
Red Sea Potable Water & Wastewater Company
Start/End Date :
2009-2012
Project Description :
Building a new desalination plant with capacity 3000 m3/day upgradable to 10.000 m3/day
- Offshore pipe intake with a diameter of 630 mm (HDPE)
- Executed by HDD (Horizontal Directional Drilling)
- Capacity 3,000 m3/day extendable to 10,000 m3/day
Reject line with a diameter of 630 mm
Services provided :
- Design calculations and detailed drawings
- Preparation of tender documents.
- Review, Approval of shop drawings, technical submittals & As-built drawings.
- Construction supervision.